2008
2009
Obtaining license
-
2010
2013
PFS; Definition Phase
-
2014
2016
International Phase; TEO Konditsii; Reserves approval
-
2017
Start of engineering of the Mining and Metallurgical Plant facilities
License ChIT14956 TE for the right to use the subsoil for mining of copper and associated minerals
Geological exploration program implemented – 75.1 thousand rm
International FS and Technical Optimization/Value Engineering Stage completed (Fluor)
Process Design Criteria for ore processing approved
Pilot plant in the vicinity of the deposit upgraded
Laboratory and pilot plant tests in SGS laboratories and at Udokan pilot plant in support of the selected flowsheet performed
JORC-compliant Mineral Resources and Reserves Estimate approved
Feasibility Study of Permanent Exploration Conditions approved
Estimation of copper reserves, associated components and minerals approved